A preliminary notice is not required.
1. Deadline to Give Preliminary Notice
2. Deadline to File Claim
Within 90 days of the date of last delivery of materials or performance of labor.
3. Deadline to File Suit or Foreclose Claim
More than 90 days but less than one year after the last day on which the claimant provided labor or materials to the project.
4. Common Questions About State Lien & Bond Claims
A. Do Suppliers to Suppliers Have Lien or Bond Claim Rights?
Suppliers to suppliers do not have lien rights.