1. Deadline to Give Preliminary Notice (Notice of the Right to Claim a Lien)

PRIVATE:
NOTE: The following requirement is for Residential Projects only. Commercial projects are not required to to provide a preliminary notice.

The notice must be given within 20 days of the first date of delivery or first performance of labor.

PUBLIC:
The notice must be given within 30 days of first date of delivery or first performance of labor.

2. Deadline to File Claim

PRIVATE:
Within 90 days of the date of last delivery or last performance of labor.

PUBLIC:
The notice must be received within 90 days after completion of contract and acceptance of work.

3. Deadline to File Suit or Foreclose Claim

PRIVATE:
Within two years after filing lien.

PUBLIC:
There is no specific provision, therefore obtain a copy of the bond, because the bond itself can set a time limit, often within one year after final payment.

4. Common Questions About State Lien & Bond Claims

A. Do Suppliers to Suppliers Have Lien or Bond Claim Rights?

On Private Projects:
Suppliers to suppliers have lien rights.

On Public Projects:
Suppliers to suppliers have lien rights.

B. Is this a Full Price Lien State:

On Private Projects:

Yes. This is a full price lien state.

On Public Projects:
Yes. This is a full price lien state.

Full Lien Summary Request Form

If you would like access to a full state lien summary, please fill in your contact information below and click “Submit.” If you have any questions about the state’s lien summary, feel free to contact our team at 206-207-0210.