STATUTORY LIENS, NON-RESIDENTIAL PROJECTS:
-Filed not later than the 15th day of the 4th calendar month after the day on which the indebtedness accrues (defined below). HOWEVER, to simultaneously protect claimant’s claim against the retainage, claimant should make sure that the affidavit is filed within 30 days after completion of the project. NOTE that where the claimant is working under a contract that is terminated, the 30-day deadline pertains to the contract under which the claimant is operating, NOT the replacement contract. Page v. Structural Wood Components, Inc. 102 S.W.3d 720 (Sup. 2003). [Schor at §44.02[D]] If a claimant has requested notice or given a notice of unpaid account, the owner is required to notify the claimant that the contract has been terminated and abandoned, and the claimant will need to file its lien accordingly. [53.107] In addition, NOTE THAT if the 15th is a Sunday or holiday, the notice must be given sooner. [Suretec Ins. Co. v. Myrex Industries, 232 S.W.3d 811 (2007)] NOTE that where claimant attempts to timely file the claim but the county clerk wrongly refuses to accept it, claimant will be allowed to enforce lien, especially where the notice of lien was timely sent to the owner and original contractor. [Ready Cable, Inc. v. RJP Southern Comfort Homes, Inc., 295 S.W.3d 763 (Tex.App.-Austin,2009).]
-Mailed to the owner and original contractor NOT LATER THAN THE FIFTH BUSINESS DAY AFTER THE AFFIDAVIT IS FILED WITH THE CLERK. Case law has held that the notice may be sent to the owner and original contractor before it is filed. [53.052, 53.055, 53.053; Arias v. Brookstone, L.P., 265 S.W.3d 459 (Tex.App.-Houston [1 Dist.], 2007); Truss World, Inc. v. ERJS, Inc., 284 S.W.3d 393 (Tex.App.-Beaumont, 2009)]
RESIDENTIAL PROJECTS, LIEN CLAIM:
The affidavit is to be filed not later than the 15th day of the third calendar month after the day on which the indebtedness accrues, and a copy mailed to the owner within 5 days of mailing. [53.052] NOTE THAT if the 15th is a Sunday or holiday, the notice must be given sooner. [Suretec Ins. Co. v. Myrex Industries, 232 S.W.3d 811 (2007)]
RETAINAGE:
The request for notice of termination or abandonment must already have been given to the owner. [53.107] (This notice is discussed above, in the preliminary notice section.]
FILED No later than the earliest of:
(a) The 15th day of the 4th calendar month after the last month in which material was furnished (the 3rd calendar month for residential projects) (if the 15th is a Saturday, Sunday or holiday, file it BEFORE that date) and not later than 30 days after the work is completed, abandoned by the original contractor, or terminated (whichever is earliest). (This deadline applies if the owner is required to send a notice of termination or abandonment, and fails to timely do so, or if the owner fails to give the claimant information about the date of the original contract, after receiving a written request from a subcontractor claimant); OR
(b) The 40th day after the date stated in an affidavit of completion as the date of completion of the work under the original contract, if the owner sent the claimant notice of an affidavit of completion in the time and manner required (see highlighted note below); OR
(c) The 40th day after the date of termination or abandonment of the original contract, if the owner sent the claimant a notice of such termination or abandonment in the time and manner required (see highlighted note below); OR
(d) The 30th day after the date the owner sent to the claimant to the claimant’s address provided in the notice for contractual retainage, a written notice of demand for the claimant to file the affidavit claiming a lien (see highlighted note immediately below).
Note that, for subsections (b), (c) and (d), if the 40th day is a Saturday, Sunday or holiday, the notice may apparently be filed on the next business day. It is recommended to avoid this situation, however. [Gov. Code 311.014]
COPY TO THE OWNER AND THE GENERAL CONTRACTOR, sent by certified or registered mail, must be sent not later than the fifth day after the affidavit is filed. [53.052, 53.057, 53.103, 53.107]
NOTE THAT if the 15th is a Sunday or holiday, the notice must be mailed or filed sooner. [Suretec Ins. Co. v. Myrex Industries, 232 S.W.3d 811 (2007)] NOTE that on non-residential projects where the general contract is terminated or abandoned, the project owner must, within 10 days after the abandonment or termination, give notice of the abandonment or termination to every subcontractor who has given the owner a preliminary notice or a request to be informed of the termination or abandonment of the original contract. This notice must include specific information, including a statement that the subcontractor must file an affidavit of lien within 30 days after the abandonment or termination, or lose its claim against the retainage. If the sub fails to file its affidavit within this thirty-day period, but otherwise complies with the notice requirements, and the owner did not provide the sub with this required notice, then the sub does not lose any rights. [53-107] NOTE that when contractor’s contract is terminated, and the contractor is replaced with another contractor, a claimant who is a sub or supplier of the original contractor must file its affidavit within 30 days after the ORIGINAL contract is terminated, NOT within 30 days of completion of the replacement contract, otherwise the claimant will lose its lien. [53.103; Page v. Structural Wood Components, Inc., 102 S.W.3d 720 (Sup. 2003)]
CONTRACT FUNDS:
Apparently mailed within the time for filing a lien, or later if the lien has been filed. [53.083]
CONSTITUTIONAL LIENS ON A RESIDENTIAL HOMESTEAD:
No specific time frame; presumably following the time frame for a residential project would suffice. [53.254; Cavazos v. Munoz, 305 B.R. 661, (S.D.Tex. 2004)]
WHEN INDEBTEDNESS ACCRUES:
Indebtedness to the original contractor accrues:
-On the last day of the month in which a written declaration by the original contractor or the owner is received by the other party to the original contract stating that the original contract has been terminated [Lyda Swinerton Builders, Inc. v. Cathay Bank, 409 S.W.3d 221 (Ct.App. Texas 14th Dist.,2013)] ; OR
-On the last day of the month in which the original contract is completed, settled, or abandoned.
Indebtedness to a sub or to supplier of labor or materials to general or sub accrues:
-On the last day of the last month in which labor or materials were supplied by the claimant.
Indebtedness for specially fabricated materials accrues:
-On the last day of the last month in which materials were delivered or would have been required at the jobsite, or
-On the last day of the month of any material breach or termination of the original contract by the owner or contractor, or of the subcontract under which the materials were furnished.
For retainage, claim accrues:
On the EARLIEST of the last day of the month in which all work pursuant to the contract between the owner and contractor is either completed, finally settled, terminated, or abandoned. [53.053]