Wyoming Lien Law Notice Deadlines

Share this valuable resource with your network:

1

Deadline to Give Preliminary Notice

Private:

Residential: Within 30 days of first performance

Public:

Within 60 days of first performance

2

Deadline to File Claim

Private:

Lien: Must see full summary as there are statutes for projects commenced before and after July 1, 2012

Public:

Bond: At the same time that a suit against the bond is commenced

3

Deadline to Foreclose

Private:

Lien: Within 180 days after filing lien claim

Public:

Bond: Within 1 year of notice of first publication of final payment to general contractor

4

Common Questions in Wyoming

Do Suppliers to Suppliers Have Lien Rights?

No

Is this a full price lien state?

No

The above guidelines are for subcontractors and material suppliers only. General contractors and design professionals may have additional deadlines and should access the Full Summary for notice requirements.

View Sample Summary of Statute »

The Lien Deadline Guides and Lien Law Summaries are provided as a courtesy. Levy • von Beck & Associates, P.S. accepts no liability in connection with reliance thereon or any loss sustained by anyone using or relying on the information contained herein. The Guides and Summaries are designed to provide a framework for understanding and dealing notice requirements and consultation with an attorney is advised.